Shandong Hongxin Yongda Foundry Technology Co., Ltd. 300,000 tons heavy casting and forging project (Phase I) Completion Environmental Protection Acceptance Monitoring Report Construction Unit: Shandong Hongxin Yongda Foundry Technology Co., Ltd. Preparation Unit: Shandong Provincial Product Quality Inspection Research Institute January 2018 Construction Project Completion Environmental Protection Acceptance Monitoring Report Lu Quality Inspection Environmental Acceptance Certificate [2018] No. 001
Shandong Hongxin Yongda Casting and Forging Technology Co., Ltd. 300,000 tons heavy casting and forging project (Phase I)
Completion environmental protection acceptance monitoring
Report
Construction unit: Shandong Hongxin Yongda Casting and Forging Technology Co., Ltd.
Preparation unit: Shandong Provincial Product Quality Inspection Research Institute
January 2018
Completion environmental protection of construction project
Acceptance monitoring report
Lu Quality Inspection Environmental Acceptance Certificate [2018] No. 001
Project name: Shandong Hongxin Yongda Casting and Forging Technology Co., Ltd. 300,000 tons heavy casting and forging project (Phase I)
Construction unit: Shandong Hongxin Yongda Casting and Forging Technology Co., Ltd.
Preparation unit: Shandong Provincial Product Quality Inspection Research Institute
January 2018
Construction unit: Shandong Hongxin Yongda Casting and Forging Technology Co., Ltd.
Legal representative: Wang Chuan Cai
Preparation unit: Shandong Provincial Product Quality Inspection Research Institute
Legal representative: Pei Hui Rong
Project leader: Wang Jing Min
Construction unit: Shandong Hongxin Yongda Casting and Forging Technology Co., Ltd.
Preparation unit: Shandong Provincial Product Quality Inspection Research Institute
Tel: 15665853102
Tel: 0531-89701987
Fax: 0531-61329922
Fax: 0531-89701987
PC: 250206
PC: 250102
Address: Guanzhuang Office, Zhangqiao District
Address: No. 31000, Jing Shi East Road, Jinan City
Monitoring undertaking unit: Shandong Provincial Product Quality Inspection Research Institute
Legal representative: Pei Hui Rong
Address: No. 31000, Jing Shi East Road, Jinan City
PC: 250102
Catalog
Preface 1
1.1 Acceptance content and purpose 3
1.2 Acceptance basis 4
1.3 Acceptance object 5
II. Overview of construction project 7
2.1 Project geographical location and layout 7
2.2 Surrounding situation of the project 10
2.3 Overview of project engineering 10
2.4 Construction content of the project 11
2.5 Main process flow and pollution generation links 15
2.6 Pollutant generation, treatment and discharge situation 17
2.7 Consumption of raw and auxiliary materials and material balance 23
2.8 Project change situation 25
III. Environmental impact assessment suggestions and requirements for environmental impact assessment approval 26
3.1 Environmental assessment conclusion and suggestions 26
3.2 Environmental assessment approval requirements 26
IV. Acceptance monitoring investigation 27
4.1 Purpose and scope of acceptance monitoring 27
4.2 Production condition inspection during acceptance monitoring period 27
V. Acceptance monitoring content 28
5.1 Waste gas monitoring factors and monitoring result evaluation 28
5.2 Wastewater monitoring factors and monitoring result evaluation 34
5.3 Noise monitoring 37
5.4 Total amount accounting 38
VI. Environmental risk prevention measures inspection and analysis 40
6.1 Waste gas risk prevention measures inspection 40
6.2 Environmental safety three-level prevention measures inspection 40
6.3 Inspection of measures to prevent hazardous waste temporary storage places 41
6.4 Inspection of primary rainwater and accident wastewater collection and drainage system 42
6.5 Inspection of various facilities for seepage prevention and corrosion prevention 42
VII. Environmental management investigation 43
7.1 Park planning environmental assessment and project industry positioning inspection 43
7.2 Environmental protection agency setup and environmental protection management system inspection 43
7.3 Emergency plan for sudden environmental events and inspection of environmental risk emergency materials 43
7.4 Management, operation and maintenance inspection of environmental protection facilities 44
7.5 Factory area greening inspection 44
7.6 Implementation of environmental monitoring plan 45
7.7 Environmental protection investment inspection 45
7.8 Investigation of disturbances during construction and trial operation period 45
VIII. Implementation of environmental assessment approval 46
IX. Public opinion survey 48
9.1 Survey time and method 48
9.2 Survey content 48
X. Conclusion and suggestions 51
10.1 Basic situation of the project 51
10.2 Environmental protection implementation situation 51
10.3 Acceptance conclusion 53
10.4 Acceptance suggestions 56
Attachment catalog
Attachment 1 Environmental impact report approval
Attachment 2 Environmental assessment conclusion and suggestions
Attachment 3 Waste steel slag, dust removal system dust export agreement
Attachment 4 Proof of relationship between Shandong Hongxin Yongda Casting and Forging Technology Co., Ltd. and New Era Heavy Industry Co., Ltd.
Attachment 5 Expert group opinion on the conformity of process technology policy of Shandong Hongxin Yongda Casting and Forging Technology Co., Ltd.
Attachment 6 Waste Mineral Oil Disposal Agreement
Attachment 7 Hazardous Waste Management System
Attachment 8 Environmental Protection Management System
Attachment 9 Explanation on the Unchanged Production Capacity of Shandong Hongxin Yongda Casting and Forging Technology Co., Ltd.
Attachment 10 Environmental Monitoring Agreement
Attachment 11 Daily Production Table During Acceptance Period
Attachment 12 Emergency Plan Filing Registration Form
Attachment 13 Anti-Seepage Certificate
Attachment 14 No Petition Certificate
Attachment 15 Oil-Containing Sludge Hazardous Waste Disposal Agreement
Attachment 16 Approval of the Application for Partial Content Change of the Environmental Impact Report of the 300,000 Tons Heavy Casting and Forging Project of Shandong New Era Metallurgical Equipment Co., Ltd.
Attachment 17 Groundwater Extraction Permit
Attachment 18 Project Rainwater and Sewage Flow Diagram
Attachment 19 "Completion Environmental Protection "Three Simultaneities" Acceptance Registration Form"